You have been assigned as the Scrum Master of six new Scrum Teams that will build one product. What conditions should you strive for in this scenario?(choose the best two answers)
Answer: C,D Next Question -
The purpose of a Nexus Sprint Retrospective is to:(choose the best two answers)
Answer: A,C Next Question -
The Scrum Teams in a Nexus find they have simply too much work each Sprint to do to deliver a valuable and useful Increment. What could they try to improve their ability to produce an Increment for the next Sprint?(choose the best answer)
Answer: A Next Question -
Scenario C: Dependencies and Product Backlog itemsDuring Nexus Sprint Planning, representatives from each of the 9-member Scrum Teams identify many dependencies. This makes it hard for them to choose the work they could pull into their individual teams for the next Sprint. No matter how they reorganize the Product Backlog items, they continually find more or new dependencies.What techniques could help this Nexus manage their dependencies effectively? (choose the best two answers)
Answer: B,D Next Question -
Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams report that it takes many hours or days to integrate their work, which delays the Sprint's end. To address this issue, which of the following would help?(choose the best answer)Integrating more frequently.Doing more acceptance testing.Doing more exploratory testing.Using Behavior-Driven Development.Investing in more Requirements Traceability.All of the above.
Answer: A Next Question -
Scenario B: Six Team Nexus with complex dependenciesA six team Nexus is developing a complex product, with different parts of the product that only certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside the Nexus that are required for some of the work. In past Sprints the Nexus encountered challenges dealing with the many dependencies between Scrum Teams.Which of the following two strategies would be most effective in dealing with their dependencies?(choose the best two answers)Discover and document dependent work during Cross-Team Refinement of the Product Backlog, so teams are aware of dependencies before Nexus Sprint Planning. This will allow Nexus Sprint Planning to focus on resolving dependencies for the upcoming Sprint.Have the Nexus Integration Team order the Nexus Sprint Backlog. They should control and resolve the dependencies.During Nexus Sprint Planning, have appropriate representatives from each team in the Nexus briefly meet to discuss dependencies for the upcoming Sprint. This conversation will help their individual team's Sprint Planning.Gather all people in the Nexus into a 48-hour Nexus Sprint Planning event. Discover, document, and resolve dependencies during this time.
Answer: A,C Next Question -
Scenario B: Six Team Nexus with complex dependenciesA six team Nexus is developing a complex product, with different parts of the product that only certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside the Nexus that are required for some of the work. In past Sprints the Nexus encountered challenges dealing with the many dependencies between Scrum Teams.Some individual Scrum Teams in this Nexus have said that they do not see how the work they are doing is contributing to the product's progress. What is the best remedy for this situation?(choose the best answer)
Answer: B Next Question -
How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?(choose the best answer)
Answer: B Next Question -
The purpose of the Nexus Sprint Backlog is:(choose the best two answers)
Answer: B,D Next Question -
True or False: A Nexus Integration Team is responsible for actually doing the integration work during the Sprint.
Answer: B Next Question