Total Questions: 86
-
The high-level technical requirements for a new application state that the application should be suitable to support enterprise-level client-server solutions. Which of the following meets these requirements?
Answer: C Next Question -
A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?
Answer: C Next Question -
Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?
Answer: B Next Question -
Which of the following communication tools would a project manager use to broadcast information without being assured the information will be received?
Answer: D Next Question -
A project manager is in the closing phase of an IT asset refresh project that involves the disposal of several computers. The project sponsor notified the project manager that the company recently received a penalty as a result of disposing of some computers improperly. Which of the following should have been considered during initial planning to prevent this situation?
Answer: A Next Question -
By developing a project schedule, a PM has already validated the constraints, outlined the duration of the tasks and the phases, and confirmed the proper sequence and flow of the project. Which of the following activities still needs to be performed to complete the schedule?
Answer: D Next Question -
As part of the planning phase, a PM has defined tasks, durations, resources, and costs. Which of the following is the NEXT step in the process?
Answer: C Next Question -
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
Answer: C Next Question -
In a functional organization, a project has been completed successfully. Which of the following actions would the project manager MOST likely perform?
Answer: C Next Question -
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?
Answer: B Next Question