You are a Product Owner. The Developers are close to the end of a Sprint and ask you for 3 extra days to complete their work. They feel that if they do not get the extra time, they might look bad in front of stakeholders, who are already skeptical of using an agile approach. What should you do? (choose the best answer)
Answer: E Next Question -
A Scrum Team is finding it difficult to get work done since team members are distracted by being pulled away to take care of work requested by other teams. The team has been regularly failing to deliver on their Sprint Goals. As a Manager, if the Scrum Team asks you for help, what should you do to solve this problem? (choose the best two answers)
Answer: A,E Next Question -
You are a manager responsible for a product being developed by a Scrum Team. A sales representative wants a particular feature in the product. They believe that it will help close a deal. The Product Owner understands the need but believes that there are more valuable things on the Product Backlog that will lead to more long-term business. The sales representative appeals to you to intervene. How do you respond? (choose the best answer)
Answer: C Next Question -
Value stream mapping is a useful technique to: (choose the best answer)
Answer: C Next Question -
Which of the following is NOT true of cross-functional teams? (choose the best answer)
Answer: C Next Question -
What traditionally "good" behavior can impede the adoption of an agile culture? (choose the best answer)
Answer: F Next Question -
Who is responsible for managing the progress of work during a Sprint? (choose the best answer)
Answer: E Next Question -
You manage a product development organization. One of your employees, a subject matter expert and a stakeholder for a product being developed, expresses that he feels that a newly-formed and relatively inexperienced Scrum Team lacks critical skills they will need to be successful. To fill this gap, he recommends replacing some members of the Scrum Team with new members who have better skills in the areas of concern. Based on these conversations, what do you do? (choose the best answer)
Answer: C Next Question -
Which statement best describes a Product Owner’s responsibilities? (choose the best answer)
Answer: E Next Question -
As a manager during your discussions with Developers, you observe that they do not feel connected to the work they are doing. They lack engagement and seem to be just going through the motions. What should you do? (choose the best answer)
Answer: C Next Question