Page: 1 / 20
Total Questions: 100
  • To achieve Neighborhood Pattern and Design Credit. Community Outreach and involvement. Option 1: Community Outreach during Preliminary Design, the project team must advertise and host at least one community meeting. Which of the following is an example of a community meeting that is applicable towards this credit?

    Answer: B Next Question
  • A project team would like to attempt the credit Transit Facilities' and is working with the local transit agency to inventory the existing and proposed bus stops within the project boundary. Oi the five proposed bus stops, one stop will be in operation at the same time when the project completes, and two stops will be in operation in the second year alter the project's completion. The remaining two bus stops will be in operation m me third year after the project's completion. How many proposed bus stops can the project team Include in the application form to attempt the credit?

    Answer: A Next Question
  • Which of the following are eligible sources of renewable energy under Green Infrastructure and Buildings Credit. Renewable Energy Production?

    Answer: B Next Question
  • For a 100% previously developed site, which of the following steps should the project team take during the Initial stages of planning to meet the requirements of Smart Location and Linkage Prerequisite. Imperiled Species and Ecological Communities Conservation?

    Answer: D Next Question
  • A LEED for Neighborhood Development project is going to temporarily reroute existing transit service outside the required distances as pan or the construction process. The protect team has secured an agreement with the transit agency to restore the rerouted service. What is the maximum number of years the service can be rerouted in order to quality tor Smart Location and Linkage Credit. Access to Quality Transit?

    Answer: B Next Question
  • The total area of all buildings on a project is 125,000 ft2 (11 612 m2). 63.750 ft2 (5.922 m2) of the project is within 1/2 mi (800 m) of 11 diverse uses and 106.240 ft2 (9.870 m2) of the project buildings are oriented for maximum solar orientation. What credit is the project eligible to achieve?

    Answer: B Next Question
  • At least how many buildings within a LEED for Neighborhood Development project must be certified by a green building rating system?

    Answer: A Next Question
  • A cultural landscape is identified on a project site. Which action contributes to Green Infrastructure and Buildings Credit. Historic Resource Preservation and Adaptive Reuse?

    Answer: D Next Question
  • According to Green Infrastructure and Buildings Prerequisite. Indoor Waler Use Reduction, the indoor water usage of a new building or buildings undergoing major renovations (nonresidential buildings, mixed-use buildings, and multifamily tour stones or more), must average at least

    Answer: B Next Question
  • A seven-story mixed-use project Has a zoning setback requirement of 40 ft. (12 m). street level retail along 75% of Its block length and an at-grade parking garage entryway along the remaining 25% of the block length. Which of the following strategies will improve the project's walkability?

    Answer: B Next Question
Page: 1 / 20
Total Questions: 100