Free Certified Lean Six Sigma Yellow Belt (CLSSYB) Exam CLSSYB-001 Exam Practice Test

UNLOCK FULL
CLSSYB-001 Exam Features
In Just $59 You can Access
  • All Official Question Types
  • Interactive Web-Based Practice Test Software
  • No Installation or 3rd Party Software Required
  • Customize your practice sessions (Free Demo)
  • 24/7 Customer Support
Page: 1 / 24
Total Questions: 120
  • One of the primary objectives of constructing an X-Y Diagram is to separate the vital few X's from the trivial many X's.

    Answer: 1 Next Question
  • In order to properly draft a Process Map at the start of a project we are told to __________________ from beginning to the end.

    Answer: 2 Next Question
  • The purpose of ________________ is to analyze data and present it in a way we can make informed decisions as to what is happening in our process.

    Answer: 2 Next Question
  • As we identify customer and supplier requirements for a SIPOC we are urged to use the RUMBA approach which stands for _____________, Understandable, Measurable, Believable and Achievable.

    Answer: 4 Next Question
  • The temperature of a liquid is being measured by a line operator. Which is least likely to be influenced by the instrument?

    Answer: 1 Next Question
  • As we begin to describe the things occurring with our process through a Process Map we begin to see some steps that are NVA which stands for ____________.

    Answer: 1 Next Question
  • The following Business Case is constructed properly. ''During most of 2008 Division 16 experienced a 4.2% product return rate versus a target of nearly no returns. This costs the company a whole bunch of money.

    Answer: 2 Next Question
  • One of the primary deliverables from performing a SIPOC is to begin to understand which inputs have the greatest affect on the ____________ most valued outputs.

    Answer: 4 Next Question
  • Measurement System Analysis is a procedure used to quantify variation of the method or system used for taking measurements and used to assure usable data is collected.

    Answer: 1 Next Question
  • To minimize waste through the application of Lean Principles we do which of the following?

    Answer: 2 Next Question
Page: 1 / 24
Total Questions: 120