Free SAP Certified Application Associate – SAP Project Systems with SAP ERP 6.0 EHP7 Exam C_TPLM22_67 Exam Practice Test

UNLOCK FULL
C_TPLM22_67 Exam Features
In Just $59 You can Access
  • All Official Question Types
  • Interactive Web-Based Practice Test Software
  • No Installation or 3rd Party Software Required
  • Customize your practice sessions (Free Demo)
  • 24/7 Customer Support
Page: 1 / 33
Total Questions: 165
  • Consider a scenario in easy cost planning where you plan dates and resources in network activities and the system automatically determines the corresponding planned costs as part of network costing.In this scenario planned costs are determined for which of the following?There are 3 correct answers to this question.Response:

    Answer: 1,,2,,4 Next Question
  • Which activity type in resource planning enables you to define service specifications and value limits for unplanned services rendered by the service provider?Please choose the correct answer.Response:

    Answer: 3 Next Question
  • Which of the following statements concerning ProMan are correct? (5)

    Answer: 2,,3,,4,,5,,6 Next Question
  • How can the capacity requirements of an activity be reduced?There are 3 correct answers to this question.Response:

    Answer: 1,,2,,5 Next Question
  • In which of the following ways Open PS allows you to exchange data directly with MS project?There are 3 correct answers to this question.Response:

    Answer: 1,,2,,4 Next Question
  • Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacity requirements and the available capacity?Please choose the correct answer.Response:Capacity planning board

    Answer: 2 Next Question
  • What is the procurement element for requirements planning?Please choose the correct answer.Response:

    Answer: 4 Next Question
  • Which of the following information regarding cost activity is not relevant for the calculation of planned costs?Please choose the correct answer.Response:

    Answer: 4 Next Question
  • Which indicator do you use to define the characteristics of a WBS element and to specify tasks that are performed by the WBS element when the project is executed?Please choose the correct answer.Response:

    Answer: 3 Next Question
  • How can you update the degree of processing for an activity?

    Answer: 2 Next Question
Page: 1 / 33
Total Questions: 165