Review sessions have been scheduled at end of Investigation, Refinement and Consolidation for the later Timeboxes to ensure that the mistakes made in Timebox A do nothappen again.Which Agile principle MOST influences this course of action?
Answer: D Next Question -
If the team cannot agree the system content, which 2 actions should the Workshop Facilitator take?
Answer: C,E Next Question -
Answer the following questions about the acceptance criteria within the project.Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.When specifying high-level prioritised requirements during Foundations, the Business Visionary has suggested that acceptance criteria for the requirement to "temporarily weatherproof the roof" should NOT be set until Solution Development Timebox
Answer: C Next Question -
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.Remember to limit your answers to the number of selections requested in each question.Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
Answer: A,C Next Question -
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?
Answer: C Next Question -
How should the Project Manager assist the electricians to deliver the wiring?
Answer: C Next Question -
Xan Insurance Company operates from one location - a large, open-plan office in the centre of a city. Those employees that will be working within the Solution Development Team are all based in this office but work at different ends of the office in separate departments.What action should the Project Manager suggest to ensure the most effective collaboration of the Solution Development Team?
Answer: C Next Question -
Answer the following questions about the acceptance criteria within the project.Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.Is this an appropriate action related to acceptance criteria?
Answer: A Next Question -
Which 2 statements explain why the Architecture Angels' Marketing Director would be an appropriate Business Visionary?
Answer: B,E Next Question -
An external web developer is to be contracted to create the new coffee bar insurance area on the existing web site. The chosen web developer will only agree to work on a 'fixed price for a fixed specification' contract.What action should the Project Manager take?
Answer: D Next Question